The last stretch of the Blue Ridge Parkway closed by Hurricane Helene has reopened, 11 miles near Mount Mitchell, in time for Thanksgiving

The Blue Ridge Parkway reopening caps the repair of more than 60 landslide sites; crews may still close single lanes as they finish work.

By Jordi Company
· 4 min read
A park employee stands at the broken edge of the Blue Ridge Parkway where the road collapsed into a slope of dirt and asphalt after Hurricane Helene
File photo: an NPS employee assesses a washout under the Blue Ridge Parkway at milepost 345, inside the stretch that has now reopened, on October 6, 2024. (Photo: National Park Service) Photo: National Park Service
Share:
Comment
Listen to the summary
1:03

Key points

  • Twelve of the repaired landslide sites were in the final stretch.
  • In North Carolina, the Parkway counted at least 57 landslides across nearly 200 miles.
  • By early October, 458 of the Parkway's 469 miles had reopened.
  • Linville Falls facilities, including the visitor center, are still being evaluated.

Drivers can once again travel the stretch of the Blue Ridge Parkway near Mount Mitchell that Hurricane Helene tore apart. The National Park Service has reopened the last section still closed by storm damage, it announced on November 21.

The 11-mile stretch runs from milepost 344 at NC-80 to milepost 355, near Mount Mitchell State Park in western North Carolina. The park calls the reopening a significant milestone in its recovery from the storm.

Helene hit the region in September 2024 with heavy rain, flooding, landslides and debris flows. It damaged roadways, bridges, overlooks and other park infrastructure along the Parkway. This fall, the state faces the opposite problem: extreme drought jumped from 10% to 26% of North Carolina in one week.

More than 60 landslides later

Since the storm, the park has restored more than 60 landslide sites along the Parkway. Twelve of them were within this final 11-mile stretch, according to the NPS.

"Hurricane Helene presented extraordinary challenges for the Blue Ridge Parkway and the surrounding region," said Superintendent Tracy Swartout. "Reaching this point reflects the dedication of our employees, contractors, partner agencies and local communities who have worked together throughout the recovery process."

"We are grateful for their continued support and look forward to welcoming visitors back to these areas in time for the Thanksgiving holiday," she added.

Three people talk in the control room of the Palisades nuclear plant in Michigan, surrounded by panels of gauges and switches
Read alsoHoltec wants to build two small reactors called Pioneer 1 and 2 next to Michigan's Palisades plant, which shut down in 2022, and the NRC is now reviewing the request

How the recovery unfolded

In North Carolina alone, the Parkway identified at least 57 landslides across nearly 200 miles, according to its project page. Work to restore access began in the fall of 2024 and was planned in three phases.

The first phase covered 13 repairs in eight areas and reopened more than 48 miles over the summer and fall of 2025. The second focused on 21 landslide areas, mainly south of Linville Falls.

The third phase covers more than 24 sites, mainly between mileposts 336.7 and 351.9. That area lies between Little Switzerland and Mount Mitchell, and the target is late 2026. The newly reopened stretch lies in that area.

As recently as October, the park said the final repairs between mileposts 344 and 355 were slated for completion and reopening by the end of 2026. The stretch reopened ahead of that target, just before the Thanksgiving holiday.

Almost there by October

By early October, the park had restored access to 458 of the Parkway's 469 miles, said Deputy Secretary of the Interior Kate MacGregor in an NPS release. Of 60 slide repairs required, she said, 48 were complete and work was underway on the last 12.

Visitors could then drive without interruption from James River, at milepost 63.7 in Virginia, to Little Switzerland, near milepost 344 in North Carolina. The newly reopened stretch starts at milepost 344.

That October update also announced two finished Helene road projects in North Carolina. One ran from milepost 317.5, south of Linville Falls, to milepost 324.7, and the other from milepost 333.9 in Little Switzerland to milepost 340.2 at NC-80.

Loops B and D at Julian Price Campground, near milepost 297, also reopened after being closed by the hurricane. Crews of arborists and volunteers cleared the way, according to the park, which called it one of its most popular campgrounds.

Some repairs used reinforced soil slopes, built from layers of soil and reinforcing materials to rebuild failed slopes. Others replaced culverts and reset stone masonry headwalls, according to the park's project descriptions.

Who paid for it

The NPS described the October openings as funded by disaster supplemental money in the American Relief Act. Its project page lists other repairs as paid for by the Emergency Relief for Federally Owned Roads program. One of them is the stretch between mileposts 317.5 and 324.7.

Some damage goes beyond the road. Park facilities near Linville Falls suffered a great deal of destruction, including the visitor center, picnic area, comfort station and parts of the campground and spur road.

Future plans for those amenities are still being evaluated, the park says. Repairs to the Linville Falls spur road have a target completion of December 2026.

What drivers should expect

Access has been restored, but construction is not completely over. Visitors should expect ongoing work in the area, including possible single-lane closures, as crews finish final repairs.

The park asks motorists to stay alert, follow posted signs and directions from work crews, and allow extra travel time. It also recommends planning ahead, since weather and maintenance can cause temporary closures.

Higher elevations can see rapidly changing weather, the NPS warns. Winter conditions may affect travel there even when lower areas remain clear. The park posts regular road status updates, facility schedules and maps on its website.

Photo: National Park Service

About the writer

Jordi Company

Writer at ECOnews

Jordi Company is a well-known figure in Catalan publishing and a pioneer of the free press model, with 40 years of experience in television, radio and print. He has founded and led several media groups and today heads ECOticias.com, an environmental news outlet read in Spanish and English around the world and an audience leader since 2004. He is a member of the International Network of Writers for the Earth (RIET), among other organisations.

More from Jordi Company

Comments · 0

Rules ›

No comments yet. Be the first to share your view.

Our newsroom reviews every comment before it is published. Links are not allowed. We only keep your nickname and your comment.

More in Science

See all →
Newsletter · Free

Green news every Monday and Wednesday, in your inbox

Hand-picked by our newsroom: the science and climate stories that matter.

We will send you an email to confirm. Every newsletter has a one-click unsubscribe link.