Holtec wants to build two small reactors called Pioneer 1 and 2 next to Michigan's Palisades plant, which shut down in 2022, and the NRC is now reviewing the request

The Palisades SMR filing came in two parts, and the NRC will announce later how the public can take part if it accepts the application.

By ECOnews Newsroom
· 3 min read
Three people talk in the control room of the Palisades nuclear plant in Michigan, surrounded by panels of gauges and switches
File photo: then-NRC Chairman Allison Macfarlane, center, and Congressman Fred Upton, left, in the Palisades control room during a June 2014 visit. (Photo: U.S. Nuclear Regulatory Commission, CC BY 2.0) Photo: U.S. Nuclear Regulatory Commission, CC BY 2.0
Share:
Comment
Listen to the summary
1:12

Key points

  • Part 1 of the application was filed on December 31, 2025.
  • The docket numbers are 50-616 and 50-617.
  • Palisades first won a provisional operating license in 1971.
  • The plant's renewed license runs until March 24, 2031.

Two new nuclear reactors could one day stand beside the Palisades plant in Covert, Michigan. The Nuclear Regulatory Commission is reviewing a construction permit application for a two-unit SMR-300 plant there, according to a Federal Register notice published November 24.

The application comes from SMR, LLC. It was filed on behalf of Palisades SMR, LLC, a wholly owned subsidiary of Holtec International. The two planned units are named Pioneer Unit 1 and Pioneer Unit 2.

The NRC received the application on September 30, 2026. It is publishing a notice of receipt each week for four consecutive weeks, starting November 10. This is the third of those notices.

A permit in two parts

Holtec is using a phased approach for the construction permit. Part 1, submitted on December 31, 2025, included a request for a limited work authorization, three exemption requests and a comprehensive environmental report.

With Part 1, the company sought NRC approval for certain early construction activities at the Palisades Energy Center. Part 2 seeks approval to complete construction of the two-unit plant.

Part 2 consists of a complete preliminary safety analysis report. It also contains a set of exemption requests from existing rules and an updated version of a quality assurance report the NRC had previously approved.

A tall lava fountain and dark gas plume rise from a vent on the floor of Halemaʻumaʻu crater at Kilauea's summit
Read alsoKilauea's 57th lava fountain lasted almost six hours and reached about 650 feet, and USGS scientists say another episode is likely in the coming weeks

The application was filed under Section 103 of the Atomic Energy Act. It also falls under Part 50 of Title 10 of the Code of Federal Regulations, the federal rules for licensing production and utilization facilities. The weekly notices are required under 10 CFR 50.43(a)(3).

Where the review stands

NRC staff are now doing an acceptance review of the application. If the agency accepts it for docketing, more Federal Register notices will follow.

Those later notices will address whether the application can be docketed and explain how the public can take part in the permitting process. The NRC's Office of Advanced Reactors is handling the review.

On November 23, the NRC also found no significant environmental impact from a fuel site in Oak Ridge, Tennessee, for 1-megawatt microreactors built by Radiant Industries.

The application is filed under docket numbers 50-616 and 50-617 and docket ID NRC-2026-0265 at regulations.gov. Part 2 is available in the NRC's ADAMS document system under package accession number ML26273A416.

A plant being restarted

The Pioneer units would sit next to an existing reactor with an unusual history. The Palisades Nuclear Plant is a pressurized water reactor about 5 miles south of South Haven, Michigan, according to the NRC.

Its reactor was supplied by Combustion Engineering and sits inside a dry, ambient-pressure containment, according to the agency's facility profile. The Atomic Energy Commission issued its provisional operating license on March 24, 1971, allowing commercial operation. The plant permanently ceased operations on May 20, 2022, after more than 40 years of commercial operation.

In early 2023, Holtec expressed interest in returning the plant to an operational status. The NRC called it a first-of-a-kind effort to restart a shuttered plant. It set up a Palisades Nuclear Plant Restart Panel to guide its reviews and inspections.

What restarting required

To restart Palisades, Holtec had to win NRC approval to restore the plant's licensing basis to operating status. It also had to bring plant components back to a state that supports safe operation and make any upgrades or repairs needed.

The NRC's records for Palisades list final documentation dated July 24, 2025, for several of those requests. They include revising the operating license and technical specifications and reinstating the emergency plan. The application to transfer control of the license is on the list too.

A license transfer filing was supplemented after a decision in the Department of Energy's loan guarantee process, the agency's page notes. The same records list final documentation dated October 30, 2025, for a request on repairing steam generators by sleeving.

The Federal Emergency Management Agency also issued reasonable assurance findings on emergency planning in September and October 2025, according to the same NRC records.

The NRC's facility page lists Palisades Energy, LLC as the operator. On August 25, 2025, the company told the NRC it was rescinding its certifications of permanent shutdown and fuel removal. The page still describes the restart as a project, and the renewed license runs until March 24, 2031.

The new application does not change that existing license. It is a separate request for two more units at the same energy center. The NRC has not yet decided whether to formally accept it for a full technical review.

Photo: U.S. Nuclear Regulatory Commission, CC BY 2.0

About the writer

ECOnews Newsroom

Writer at ECOnews

A team of journalists specializing in socio-environmental news, sustainability, climate change, the environment, responsible consumption, and innovation. At EcoNews, we provide clear, reliable, and relevant coverage of the environmental and social challenges shaping our era.

More from ECOnews Newsroom

Comments · 0

Rules ›

No comments yet. Be the first to share your view.

Our newsroom reviews every comment before it is published. Links are not allowed. We only keep your nickname and your comment.

More in Science

See all →
Newsletter · Free

Green news every Monday and Wednesday, in your inbox

Hand-picked by our newsroom: the science and climate stories that matter.

We will send you an email to confirm. Every newsletter has a one-click unsubscribe link.